page 1
page 2
page 3
page 4
page 5
page 6
page 7
page 8
page 9
page 10
page 11
page 12
page 13
page 14
page 15
page 16
page 17
page 18
page 19
page 20
page 21
page 22
page 23
page 24
page 25
page 26
page 27
page 28
page 29
page 30
page 31
page 32
page 33
page 34
page 35
page 36
page 37
page 38
page 39
page 40
page 41
page 42
page 43
page 44
page 45
page 46
page 47
page 48
page 49
page 50
page 51
page 52
page 53
page 54
page 55
page 56
page 57
page 58
page 59
page 60
page 61
page 62
page 63
page 64
page 65
page 66
page 67
page 68
page 69
page 70
page 71
page 72
page 73
page 74
page 75
page 76
page 77
page 78
page 79
page 80
page 81
page 82
page 83
page 84
page 85
page 86
page 87
page 88
page 89
page 90
page 91
page 92
page 93
page 94
page 95
page 96
page 97
page 98
page 99
page 100
page 101
page 102
page 103
page 104
page 105 page 106
page 107
page 108
page 109
page 110
page 111
page 112
page 113
page 114
page 115
page 116
page 117
page 118
page 119
page 120
page 121
page 122
page 123
page 124
page 125
page 126
page 127
page 128
page 129
page 130
page 131
page 132
page 133
page 134
page 135
page 136
page 137
page 138
page 139
page 140
page 141
page 142
page 143
page 144
page 145
page 146
page 147
page 148
page 149
page 150
page 151
page 152
page 153
page 154
page 155
page 156
page 157
page 158
page 159
page 160
page 161
page 162
page 163
page 164
page 165
page 166
page 167
page 168
page 169
page 170
page 171
page 172
page 173
page 174
page 175
page 176
page 177
page 178
page 179
page 180
page 181
page 182
page 183
page 184
page 185
< prev - next > Energy Hydro power civil_works_guidelines_for_micro_hydro (Printable PDF)
CIVIL WORKS GUIDELINES FOR MICRO-HYDROPOWER IN NEPAL
103
Photo 6.14 Penstock at Ghandruk with village in the background
Photo 6.13 Sliding expansion joint, Jhankre mini-hydro
The following coats of paint are recommended:
Outside surface of above ground mild steel pipes
First two coats of primer should be applied on the pipe surface.
Red Oxide Zinc Chromate primer is appropriate for this purpose.
Then another two coats of high quality polyurethane enamel
paint should be applied on top of the primer.
Outside surface pipe of which will be buried or cast into
anchor blocks
Two coats of primer similar to above ground pipe should be
applied. Then, another two coats of high-build bituminous
paint should be applied over the primer. Provide an extra coat
of bituminous paint at transition areas, which are more prone
to corrosion (see Figure 7.1).
Inside surface of pipes
For small diameter pipes it may not be possible to paint the
inside surface. However whenever possible, the inside surface
should be painted with two coats of good quality red lead
primer. If there is a doubt about the quality of paint, the
supplier’s specifications should be checked prior to its use.
Note that paintwork is not required for HDPE or PVC pipes.
Any paintwork damaged during transport and installation
must be made good, so that the full number of coats is present
everywhere. This is especially important for buried pipes.
6.12 Installation
The following procedure should be used:
The centreline of the penstock should be set out using a
cord and pegs along the selected route as shown in Figure
6.8. For micro-hydro schemes above 20 kW of installed
capacity, a theodolite should also be used to ensure that
the bend angles correspond to the fabricated pipe bends.
A line should be marked by spreading lime on the surface
of the ground to replace the cord. Then the positions of
anchor blocks and support piers should be marked to the
required spacing for exposed pipes and excavation carried
out along this line as required.
For buried pipes, the penstock is installed in the excavated
trench and backfilled as shown in Figure 4.8. The backfill
should be rammed in layers and a slight hump above the
level of the ground helps to keep the alignment dry. An
improperly backfilled penstock alignment can quickly become
the route for drainage water down the hillside. However,
note that backfill should be completed only after the pipe
has been pressure tested.
For exposed pipes, the anchors and supports should be
constructed as will be discussed in Chapter 7. The pipe
should be cast into the anchors and placed on one support
pier at a time. No further supports or anchors should be
built until the pipe is secured to the previous anchor block
or support pier. For both site welded and flange connected
pipes, the end should protrude from the last support block
with adequate margin (~ 300 mm) so that either the flange
or the weld line does not lie on the support pier during
thermal expansion or contraction. If more than one pipe
section needs to be welded between the support piers,
temporary supports should be used as shown in Photograph
6.15. Flange connected pipes should be joined and the
bolts tightened as the installation progresses.
The installation of the penstock should start from the
machine foundation and proceed upstream. This avoids
any misalignment between the penstock and the turbine
housing. Since the turbine needs to be firmly fixed to
the machine foundation, there is almost no tolerance at
this end after the machine foundation has been
constructed. Furthermore, the pipe sections below the
expansion joints can slide down if installation proceeds
downstream from the forebay. Minor pipe deviation can
be adjusted at the forebay wall, but such adjustment is